What work is happening?
Starting on 4 January 2027, the top gate at Autherley Junction Stop Lock will be replaced.
One gate leaf measures approximately 2.7 metres wide and 1.9 metres tall, and weighs around 1400kg - which is roughly the weight of an adult male giraffe, or small pick-up truck.
We hope this work will be complete by 12 March 2027.
What does this mean for canal users?
Both the navigation and towpath will be closed during this period.