Skip to main content

The charity making life better by water

Boaters' Update 25 Sep 2025

Update after recent rain, helping you home, massive project completes, winter moorings and much more in latest edition.

Rock bags in canal viewed from above Repairing the embankment on the Huddersfield Narrow Canal

Water resources update – when will restrictions ease?

As you’ll be aware, it has been raining. This is navigationally very welcome, of course, but what impact have the recent deluges had on your canal network after the preceding months of parched conditions?  Whilst some canal reservoirs can respond quite quickly to rainfall, only last week, the National Drought Group warned that ‘the current drought is far from over despite the recent rain.’

To understand the implications of the recent weather, and if it’s yet resulting in the lifting of navigational restrictions, Dr Adam Comerford, our national hydrology manager, had this to say: “The recent rainfall we’ve seen across the network has been very welcome, after such a prolonged period of drought, the worst for many years. For England, last week’s rainfall (43mm, the week up to 16 Sept) was the most seen in any single week since January, and the rainfall overall (to date) this month is above the September Long Term Average.  But we’re not out of the woods yet, unfortunately, and the waterway network is not able to fully reopen yet. 

“This is because many of our reservoirs have failed to see any notable recovery from their historic low water levels, and whilst many canal pound levels have shown some useful replenishment, we cannot yet fully reopen as we would still need to draw water from the reservoirs.

“There are, however, some aspects of positive news. Following localised heavy rainfall, the very rapid recovery of level (and hence water holding) in Winterburn Reservoir, which rose over six metres in the space of just four days, the Leeds & Liverpool Canal has been re-opened, albeit with some restrictions still in place (see our notice).  Interestingly, none of the other reservoirs in the Leeds & Liverpool group showed any significant recovery in levels, highlighting that we need the rainfall to arrive in the right place to make a real difference!

“Several other canals have seen enough recovery in their water resources situation to provide partial or complete reopening, but as always, we would ask customers to check our notices pages here to find out the latest situation, which as I’m sure you can appreciate, continues to change quite rapidly as the autumn rainfall arrives.  It is worth noting that as some canals have been closed for many months, refilling and then reopening may not happen immediately, as our teams need to clear vegetation and debris that may have built up at locks as well as checking and inspecting structures that have been out of water or unused for a prolonged period.”

While it's too early to say that we're out of the proverbial woods, increased rainfall has enabled us to start planning for the lifting of some restrictions in the Oxford and Grand Union hydrological unit - read more here.

Toddbrook Reservoir works on spillway

Helping you home

With winter approaching we want to do all we can to assist those looking to return to a home mooring or winter mooring.   As the unprecedented drought of 2025 continues to affect our waterways and navigation, we understand that some boaters remain unable to return to their home mooring due to ongoing closures, and with planned winter stoppages approaching, there may be further delay for those already impacted.

While the reopening of waterways depends largely on rainfall, we are actively reviewing options to support boaters who cannot reach their intended destination. To do this effectively, we first need to understand the scale of the issue and hear from those directly affected.

If this applies to you, please take a few minutes to complete this form linked. Your input will help us assess the situation and explore what support may be possible.

Thank you for your cooperation, and patience, during these challenging conditions.

Big issues, big solutions

It is ironic that one of the major projects that has been completed this summer has been the repair of damage caused by stormy wet weather last new year’s eve.

I am, of course, talking about Lock 11W on the Huddersfield Narrow Canal. As a brief reminder, there was a major landslip on the offside banking caused by the intense rainfall and saturated hillside. In the video below, Simon Sutherland, senior project manager, Chris Caple, principal engineer and Leon Edmondson, area operations manager, talk about the challenges, and solutions, of the repair.

  • Transcript

    We are on the Huddersfield Narrow Canal in between Mosley and Staley Bridge. A storm event occurred at the late Christmas period into the early new year, and that caused two large scale slips between the canal embankment and the River Tame.

    Our response to this emergency situation was that we had to close the canal here between Scout Tunnel to the north and all the way down to Lock 9 west in the south section of this canal. We've had to remove 1,200 tons of material all before we could start to reinstate the embankment of the canal.

    As part of that reinstatement, we've now installed 900 rock bags into this location and we have then covered the rock bags in topsoil and coir matting. Our biggest challenge on this project has been access – this section of the canal is rather remote. We've had to create two access points working with third party landowners. We've also had to create an access point across the canal at one location and we've had to cross the River Tame at another location.

    With the drought conditions that we've currently been experiencing, that has really helped us to get this work done and completed as quickly as possible as part of our design development and engineering solution. It's been a massive team effort. We've worked very closely with Chris Capel in design and development, with Bentley’s, and with our colleagues in heritage, environment, and ecology.

    This work in total is probably going to be about £1.4 million. The solution that we've come up with was to use the rock bags, which have probably saved the Trust at least a couple hundred thousand pounds in both time and material.

    The work here is almost complete. We are just finishing off, but we have got some additional works to complete in the near future. We'll be doing some grouting to the lock and we will be looking to increase the size of a weir upstream of this location, just to add a little bit of resilience with regards to water coming downstream. The towpath is open, and if it wasn't for the drought conditions that we're currently experiencing, the navigation would be back open.

    A big thank you from myself and the rest of the project team to the people who have supported us through this year. We've had massive help from operations, from asset management, and across the wider project delivery team. It's been a huge team effort and everyone's worked collaboratively to get this canal back open as quickly as possible.

    Our team offers design engineering support for the high-priority works teams and for the priority projects, including arising emergency jobs. We believe these slips were caused by a couple of factors during these storms in the winter between Christmas and New Year's. There was a lot of water in the canal, a lot of water in the river, and a combination of the river scouring away the toe of the embankment, along with overtopping from the canal and potentially some leaks from the wash wall. All these things combined to give a very saturated slope, which then slipped.

    I got involved pretty early on – I came a few days after the slips and provided the design for the repair. I researched potential solutions for this sort of project. Initially I looked at things like gabions and concrete walls, but these are both quite labour intensive in and around the fragile structure that’s left. Then I came across these rock bags. They're fairly innovative, providing a lot of stability. They act like a gabion basket, but are more flexible. Over time they interlock once they're placed, acting as one solid mass and providing strength to the slope.

    In total, we used about 900 rock bags. Other things we’ve done to add resilience include raising the towpath at the south slip, which was clearly a low point, and looking at increasing the size of the weir to the north of the lock to prevent overtopping in future.

    We are seeing a lot of these arising emergency issues. Much of this is down to the nature of the infrastructure – it’s 250 years old. It's very old and would normally be at end of life, but we’re working hard to extend that life all the time. That’s where a lot of our work goes.

    I remember the night of the weather. There was a lot of activity in the group chat because some of my team had been called out. I was actually off work the next day, but I decided to come in because I knew the team would need instruction and guidance, and that the escalation process needed to be kicked off.

    When I visited the site, I was dumbstruck with what I saw. I know the Trust has experienced worse infrastructure damage over the years, but in my 16 years here I’ve never seen anything like that. I remember thinking, “Right, where do we start trying to fix this?” After that initial shock, I took a few steps back and thought, “Let’s just make it safe.” We needed to get an on-site assessment underway and make the area inaccessible so people weren’t putting themselves at risk. Instinctively, people are nosy – if something’s wrong, they will have a look, and in doing so could put themselves in harm’s way.

    We fenced the site off at either end, fenced the lock, and then I started the escalation process. I spoke to my manager, he spoke to his, and it went all the way up to the top. I remember communication between myself, Steve Ballard and Julie Sharan, and that was maintained throughout the day. The next step was reaching out to all the departments that needed to be involved – asset management and others. Within hours, everyone felt confident that we were doing the best possible thing we could.

    Meanwhile, my team supported contractors with water control – maintaining water levels, installing dams, fencing, and carrying out minor operational repairs. When the site demobilises, we’ll need to take the fencing away, test the lock, and make sure everything is still operational and fit for purpose before reopening.

    Coincidentally, whilst all this has been going on, the canal’s been closed because of this defect, but we would have had to close anyway due to water shortages. This has been an issue on my patch and across the region – for example, on the Rochdale Canal, where we’ve struggled to maintain water levels. Fortunately, as this project comes to completion, water levels are resolving themselves. So it looks like we’ll be able to open at the same time as the defect is repaired.

Annual Public Meeting

Don’t forget that our Annual Public Meeting will take place live online at 2.30pm on Monday 20 October. During the meeting we'll reflect on our activities and financial performance during 2024/25 and welcome our new CEO, Campbell Robb.

You will be able to join the event on the day via our website homepage. If you have a question that you'd like to submit, please send it to [email protected].

Winter moorings on sale next week

While autumnal weather may have only just arrived, believe it or not, there are only 91 days until Christmas. Many of you will have already made plans to winter in a certain location by purchasing a Trust winter mooring.

If this is you then next Thursday, 1st October, you’ll be able to secure your winter mooring. The full list of winter moorings is listed on our website. Some may be currently affected by current drought navigation closures/restrictions, but with the navigational picture changing quite quickly in many instances, we will update the list before they go on sale according to the situation at that time. We appreciate that this will impact on plans for the winter months and ask for your patience and understanding.

Buying your permit

Permits will be on sale on a first come, first served basis, from 8am on Tuesday 1 October and you'll be able to buy your winter mooring permit online.

If you are a current boat licence holder but you don't have an online account with us, please choose the option to register but make sure you fill in your details within the ‘I am an existing Canal & River Trust customer’ section.

Snow on the Llangollen Canal Snow on the Llangollen Canal

Maintenance, repair and restoration work this weekend

As the above update demonstrates, the network wasn’t built for extreme weather and it does impact its ability to operate which sometimes mean we have to reluctantly restrict, or stop, navigation.

When this does happen, we get notices up on to our website as soon as we can – it’s always best to have a scan while you’re planning your cruise and also just before you set off. You can find out how to get stoppage notification alerts on your smartphone in this article.

A map of the areas affected by low water levels can be found on the Notices section of our website: filter by reason: ‘Low Water Levels’ and select ‘Map View’. If you think you’ll be regularly checking the map then bookmark this link and it’ll take you straight to the low water stoppage map.

Below, you’ll find a list of navigations that have ongoing restrictions not related to low water levels that may affect you if you’re planning to get out on the water this weekend:

If you have any questions about a specific closure, or spot an error in our system, please get in touch.

Partnership quickly produces results

Volunteering at the Canal & River Trust continues to go from strength to strength, assisting our charity in a huge variety of tasks, with people bringing diverse skills and always huge amounts of enthusiasm.  Last week I was struck by this message of thanks from CyanLines for volunteers on the Rochdale Canal for ‘answering our call to clean up the Rochdale Canal behind Deansgate’. Check out the before and after photos below:

For more details on how you can volunteer to help please visit our website.

Last Edited: 25 September 2025

photo of a location on the canals
newsletter logo

Stay connected

Sign up to our newsletter and discover how we protect canals and help nature thrive