Descriptions
Update 16 September 2026, 4:46pm
Since our last update we are still awaiting confirmation of a start date for the grouting works which is part of the National Grouting Programme which has been delayed on other priority work. Until this date is confirmed Lock 63 towpath side still remains open for navigation.
A further update will be provided on or before Wednesday 7 October.
Original 25 August 2026, 2:25pm
Navigation is closed at Lock 63 offside, Clearwater lock on the Trent & Mersey Canal, due to leakage.
The repairs have been included as part of our National Grouting Programme. Until a date is confirmed for the grouting works, Lock 63, Towpath side remains open for navigation.
A further update will be provided on or before Wednesday 16 September
