Between Coleshill Road Bridge 41 and Bridge 40, Taverners Bridge, Atherstone

Type: Navigation Restriction

Waterway(s): Coventry Canal

From: 13 July 2026, 8am

To: 30 September 2026, 5pm inclusive

Region: West Midlands

Reason: 3rd Party Works

Location

Closest waterwayCoventry Canal
Starts atBridge 41, Coleshill Road Bridge
Ends atBridge 40, Taverners Bridge

Descriptions

Update 26 August 2026, 4:05pm

Please be advised that the completion date for the ongoing third-party works has been extended and is now expected to be 30 September 2026.

The extension is required due to delays in the construction programme.

As a result, the suspension of moorings associated with these works will also remain in place until 30 September 2026.

We apologise for any inconvenience this may cause and thank you for your patience and understanding while the works are completed.

Original 9 July 2026, 12:21pm

Third-party contractors on Behalf of Deeley Homes are to undertake canal wall repairs following the demolition of the old Britannia Warehouse.

A fabric dam will be installed in the canal to facilitate the works. The works will be undertaken in two phases (70m sections) to minimise disruption to canal users.

One to two visitor mooring spots next to Coleshill Road Bridge 41 may need to be suspended for a period of three to four weeks.

Please adhere to signage on site and pass the dam with care, we apologise for any inconvenience this may cause.