Descriptions
Update 20 May 2026, 4:13pm
Third party contractors have been delayed attending site, and have had to reschedule to complete the repair at Lock 94B on the Rochdale Canal on the 1 June.
A further update will be provided on or before Tuesday, 30 June.
Original 19 May 2026, 5:12pm
Third-party contractors will be onsite at Bridge 94B, Rochdale Canal to carry out maintenance work, which is required to repair brickwork on the bridge and to remove vegetation.
Please allow sufficient time for the contractors on site to clear the area and permit safe passage. A delay of no more than 30 minutes is anticipated.
A further update will be provided on or before Friday, 5 June.