Original 5 March 2026, 3:30pm
Plough dredging will be taking place on the River Trent between Stoke Lock and Torksey Lock from Friday, 6th March 2026 and progress to other lock sites as per the schedule below, with completion on Wednesday, 25th March 2026:
| Location | Duration | Dates |
|---|---|---|
| Stoke Lock | 3 days | 6th March - 10th March |
| Gunthorpe Lock | 1 day | 11th March |
| Hazleford Lock | 2 days | 12th March - 13th March |
| Newark Nether Lock | 1 day | 16th March |
| Cromwell Lock | 4 days | 17th March - 20th March |
| Torksey Lock | 2 days | 23rd March - 24th March |
The navigation and towpath will remain open but there may be delays to move plant and equipment.
Please be aware of increased activity, proceed with care and follow any guidance from staff on site.