Description
Original 11 December 2025, 3:27pm
As part of the installation of the 66kV XLPE Power Cable circuit across Kensal Green substation and Powergate datacentre via the Grand Union Canal Towpath.
Snagging and remedial works across will be undertaken across completed cable sections (JB 1/2 to JB 5/6) through Ladbroke Grove to Old Oak Lane.
Installation of link pillar foundations, Installation of footing for Hythe Road footbridge and any other outstanding tasks to completion.