Update 14 September
Work has temporarily stopped on the reconstruction of the canal embankment due to unforeseen wet areas of material at the south (New Mills Lift Bridge) end of the works. The wet areas are preventing the imported granular material from being adequately compacted.
The existing dams at the south end of the works are to be moved further back in an attempt to reduce water ingress, believed to possibly be infiltrating from the adjacent canal. Additional remedial work is planned to improve the ground using soil stabilisation techniques to allow works to recommence.
We will keep you updated with progress over the next few weeks.
Update 10 August
We have now completed the reinstatement of the flooded field and repairs to the culvert inlet and outlets. The footpath has been re-opened and the field will be re-seeded with stockproof fencing installed over the next few months. The embankment reconstruction is due to start this week.
The embankment is to be 115-metres long x 5.8-metre high, with 45-degree steep side slopes. It will be constructed using approximately 14,000 tonnes of compacted granular aggregate with geogrid reinforcement at approximately 0.6-metre vertical spacing over its width. A draft design of the concrete canal channel has been completed and is now being finalised for construction purposes. This will be 9.5-metres wide x 1.6-metres deep. Construction of this channel will start once the embankment is complete. Water is continuing to be pumped around the breach with additional pumps being provided to provide resilience and extra pumping capacity. We will continue to provide updates as work progresses.