Update 8 June
Our contractors have now completed the removal of around 4,000 tonnes of sand and re‑graded the field that was previously flooded. The buried culvert has been fully cleared and is flowing again.
Work is now focused on excavating the remaining embankment back to the original breach profile. Material is being carefully removed using tracked excavators and dumpers, with stockpiles created on site before being taken away for reuse elsewhere.
Preparations are underway for the embankment reconstruction, which will involve backfilling in layers and installing geogrid reinforcement to strengthen the structure. Wherever possible, material recovered from the site will be reused. Because the site has only a single access point, operations are being managed as efficiently as possible using specialist plant.
Water continues to be diverted by pumping around the breach. An alternative flume system was explored, but due to limited space on site it was not feasible to progress.

