Bridge 37, Hazelhurst Bridge, Caldon Canal

Detail

From Date: 05/09/2022 08:00

To Date: 06/04/2023 17:00 inclusive

Type: Navigation Closure

Reason: (Re)Construction

Is the towpath closed? Yes

Location

Closest waterway: Caldon Canal

Starts at: Lock 10 Hazelhurst Top Lock

Ends at: Access Point

Upstream winding hole: Cheddleton Flint Mill

Downstream winding hole: Hazelhurst Junction

Updates

10/03/2023 14:10

We would like to update our customers regarding the ongoing works at Bridge 37, Hazelhurst. There have been several challenges which have resulted in the requirement to extend this stoppage by 2 weeks. Taking the end date to 06/04/2023. A rebuild of the waterway wall on the southern side of the canal is required. The extent of this only became visible as construction reached that point and we were able to fully assess it.   A review of the work methodology was required as there is now a need for a dam to enable the navigation to be dewatered so the wall can be repaired in dry conditions. We have worked closely with our contractor to enable the navigation to be open ahead of Easter.   We will be using pontoons once the navigation is open to lay brickwork. This will mean that a navigation restriction will be put in place and boaters will be asked to wait for a period of up to 2 hours whilst construction activities are moved aside to enable passage. The restriction will run until 19/05/2023 and a separate notice will be in place for this.   There’s no current expectation that the delays will affect the final completion of the project, although the towpath closure is expected to extend to 13th July, again this will be advised via an individual notice.   We thank you for your understanding and apologise for the inconvenience caused. 

13/02/2023 10:16

The end of this stoppage will now be 06/04/22.

Please refer to separate notice:

https://canalrivertrust.org.uk/notices/22270-bridge-37-hazlehurst

05/08/2022 17:35

  • The £2 million project will take approximately 12 months, and is due to be completed by August 2023.  Full information about the project is now available on our website at www.canalrivertrust.org.uk/hazelhurstbridge

Please note that while the canal will remain open to navigation up to the bottom of Hazelhurst Aqueduct, there is no winding hole above Cheddleton Flint Mill.

Description

Please be advised we will be closing this section of the canal to facilitate the building of a new bridge.

Further information about the project can be found here:

https://canalrivertrust.org.uk/news-and-views/news/gbp2-million-hazelhurst-bridge-restoration-work-to-begin-early-august