Updates
31/07/2016 11:45
We have now managed to get the water levels up to the required levels for navigation.
Although their is damage to the cill on the bottom gates of the lock we feel that at this stage we are able to open the lock up for boats to pass through.
We will continue to monitor the water levels and the cill over the coming days.
Thank you for your cooperation and support.
29/07/2016 10:15
We are continuing to monitor the water feeds along the canal above Shardlow lock.
We have increased the feed of water at Wychnor which comes off the River Trent.
Unfortunately we suffered some anti social behavior at Dallow lock during last night which has slowed the recovery process down.
The team are working the system between Wychnor and Shardlow to get as much water through in an attempt to recover the levels
28/07/2016 17:20
The team this afternoon have managed to realign the bottom gates.
We are now in the process of checking the water feeds and weir crests, in an attempt to maximum the flow of water in to the pound above the lock in order to raise the water level.
A further update will be issued tomorrow morning