A13 Refurbishment works to Road Bridge spanning over Bow Creek.

Starts: 12 August 2024 07:00 am

Ends: 1 October 2025 06:00 pm inclusive

Type: Advice

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterwayBow Creek

Description

Please be aware a third party will be carrying out the following works.

-Steelwork Refurbishment & Strengthening.

- Renewal of Corrosion Protection system.

- Concrete repairs to abutment.

During High Tides there will be a 10-metre-wide open channel under the bridge for navigation to pass safely through. Advanced warning signage will be positioned 100m and 200m both upstream and downstream to warn boaters navigating through the works site.