Near Bridge 1B (East Croft) - Nottingham Beeston Canal

Starts: 24 March 2023 08:00 am

Ends: 31 December 2024 11:45 pm inclusive

Type: Navigation Restriction

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterwayNottingham & Beeston Canal
Starts atBridge 1b East Croft
Ends atBridge 1b East Croft

Updates

26/11/2024 09:49

Contractors continue with the maintenance works on the gas pipes at Bridge 1B (east Croft).

These works are now scheduled to be completed by 31st December.

Pontoon and scaffold are in the waterway, to the east of the navigation. The scaffold is erected around the gas pipes which will reduce towpath width.

Navigation and towpath users should proceed with care and follow advice on site.

25/10/2024 11:58

Contractors continue with the maintenance works on the gas pipes at Bridge 1B (east Croft).

These works are now scheduled to be completed by 30th November.

Pontoon and scaffold are in the waterway, to the east of the navigation. The scaffold is erected around the gas pipes which will reduce towpath width.

Navigation and towpath users should proceed with care and follow advice on site.

04/09/2024 09:31

Contractors continue with their maintenance works on the gas pipes at Bridge 1B (east Croft).

These works are now scheduled to be completed by 31st October.

Pontoon and scaffold are in the waterway, to the east of the navigation. Scaffold are around gas pipes which will reduce towpath width.

Navigation and towpath users to proceed with care and follow advice on site.

06/08/2024 13:25

Contractors continue with their maintenance works on the gas pipes at Bridge 1B (east Croft). These works are now scheduled to be completed by 30th August.

Pontoon and scaffold will be in the waterway, to the east of the navigation. Scaffold will be around gas pipes which will reduce towpath width. Navigation and towpath users to proceed with care and follow advice on site.

04/06/2024 08:50

Contractors will resume their maintenance works on the gas pipes at Bridge 1B (east Croft) on 5th June. These works are now scheduled to be completed by 30th June.

Pontoon and scaffold will be in the waterway, to the east of the navigation. Scaffold will be around gas pipes which will reduce towpath width. Navigation and towpath users to proceed with care and follow advice on site.

25/04/2024 15:36

Contractors will resume their maintenance works on the gas pipes at Bridge 1B (east Croft) on 8th May. These works are now scheduled to be completed by 30th June.

Pontoon and scaffold will be in the waterway, to the east of the navigation. Scaffold will be around gas pipes which will reduce towpath width. Navigation and towpath users to proceed with care and follow advice on site.

25/01/2024 13:55

Delays in reducing the gas pressure within the pipeline persist, further postponing the repair and subsequent re-coating efforts.

Waterway and Towpath users are asked to proceed with care and follow advice on site.

This notice will be updated on 30th April 2024.

28/11/2023 11:57

Delays in reducing the gas pressure within the pipeline persist, further postponing the repair and subsequent re-coating efforts.

Waterway and Towpath users are asked to proceed with care and follow advice on site.

This notice will be updated on 31st January 2023.

02/10/2023 12:17

A pontoon and scaffolding will continue to occupy the waterway at Bridge 1b, East Croft, Nottingham on the Nottingham Beeston Canal.

Delays in reducing the gas pressure within the pipeline persist, further postponing the repair and subsequent re-coating efforts.

Waterway and Towpath users are asked to proceed with care and follow advice on site.

This notice will be updated on 30th November, 2023.

11/08/2023 11:06

A pontoon and scaffolding will continue to occupy the waterway at Bridge 1b, East Croft, Nottingham on the Nottingham Beeston Canal.

Delays in reducing the gas pressure within the pipeline persist, further postponing the repair and subsequent re-coating efforts.

Waterway and Towpath users to proceed with care and follow advice on site.

This notice will be updated on 15th September, 2023.

16/05/2023 16:51

Due to a leak on the gas main, the third party contractor maintenance and re-coating of the gas pipes which cross the canal at Bridge 1B (East Croft), has been extended to 31st May.

06/04/2023 15:07

Due to a leak on the gas main, the third party contractor maintenance and re-coating of the gas pipes which cross the canal at Bridge 1B (East Croft), has been extended to 15th May.

24/03/2023 17:45

Contractors will be carrying out maintenance and re-coating of the gas pipes which cross the canal at Bridge 1B (East Croft), Nottingham..

Pontoon and scaffold will be in the waterway, to the east of the navigation. Scaffold will be around gas pipes which will reduce towpath width. Works will take place from the 24th March until the 7th April.

Waterway and Towpath users to proceed with care and follow advice on site.

Description

Contractors will be carrying out maintenance and re-coating of the gas pipes which cross the canal at Bridge 1B (East Croft), Nottingham..

Pontoon and scaffold will be in the waterway, to the east of the navigation. Scaffold will be around gas pipes which will reduce towpath width. Works will take place from the 24th March until the 7th April.

Waterway and Towpath users to proceed with care and follow advice on site.