Bridge 37, Hazelhurst Bridge, Caldon Canal

Starts: 6 April 2023 05:00 pm

Ends: 17 July 2023 04:10 pm inclusive

Type: Navigation Restriction

Reason: (Re)Construction

Is the towpath closed? Yes

Location

Closest waterwayCaldon Canal
Starts atBridge 37
Ends atBridge 37

Updates

17/07/2023 16:10

We have now completed works to rebuild the Grade II listed Hazelhurst bridge.The navigation and towpath are now open.

16/06/2023 12:55

Navigation restrictions are being extended by three weeks until 7 July, to allow for further bridge works which involve working off pontoons.

We apologise for any inconvenience caused.

15/05/2023 13:04

We have had to extend the navigation restriction to Friday 16th June.

We apologise for any inconvenience caused.

13/03/2023 12:06

Please be advised there was an input error with the passage times on the previous update.

Passage will be available twice per day from:

9am to 10am and 1:30pm to 2:30pm.

10/03/2023 15:42

Passage will be available through the site twice per day 9.00am to 10pm & 1:30pm to 2:30, Monday to Friday. For boats travelling west, our contractors will facilitate the operations of the adjacent lock so that boaters do not have to get off their boats. Travelling east, boaters should be able to operate the lock adjacent themselves.

Unrestricted passage will be available evenings from 5pm and mornings until 7:30am and throughout weekends and bank holidays, including the full Easter Weekend. The contractors will leave the site so that boaters can operate the locks from both directions without assistance.

The towpath on the main line (through the locks) will remain closed from Hazelhurst Junction to Hazelhurst Aqueduct, however boaters will be able to get on and off to operate all locks within this fenced section

Please be advised that there is still a physical restriction in height - 2100mm minimum height is still available, equating to a reduction of circa 300mm from previous..

Signage will be posted to advise boaters of these restrictions.

Further information about the project can be found here:

Hazlehurst Bridge restoration work to begin in August | Canal & River Trust (canalrivertrust.org.uk)

Description

Please be advised there will be restrictions to this canal section underneath Bridge 37 to facilitate the building of a new bridge.

Restriction will be a minimal reduction in height (circa 300mm from previous) in the new bridge location to facilitate construction.

Further information about the project can be found here:

https://canalrivertrust.org.uk/news-and-views/news/gbp2-million-hazelhurst-bridge-restoration-work-to-begin-early-august

photo of a location on the canals
newsletter logo

Stay connected

Sign up to our monthly newsletter and be the first to hear about campaigns, upcoming events and fundraising inspiration