Updates
28/08/2020 13:00
the maintenance team have successfully completed the repairs to Meadow Lane lock.the lock is now open to boat traffic.we appreciate our customers patience during this unplanned stoppage.
28/08/2020 13:00
the maintenance team have successfully completed the repairs to Meadow Lane lock.
the lock is now open to boat traffic.
we appreciate our customers patience during this unplanned stoppage.
14/08/2020 16:15
The Crane boat arrived on site on Thursday and our maintenance team have been working hard to clear out all the stone and debris from the lock, and cut off the twisted escape ladder.
Our Structural Engineer has been on site and carried out a further assessment. Based on this assessment, we estimate the repair works to take approximately two weeks.
As we receive more information and progress reports with regards this stoppage, we will update our website accordingly.
11/08/2020 14:49
We have been advised that the repair works at Meadow Lane, will need to be carried out by one of our Crane Boats.
This is currently on route to site and should be at the location by Thursday Evening, ready for works to commence on Friday morning.
Our maintenance team will firstly need to clear out all the stone and debris from the lock, and cut off the twisted escape ladder.
There are many large stone blocks below water. They will then be able to carry out a full assessment with our structural engineer on site.
Once this assessment is completed, we will know the full extent of the damage caused and be able to plan what repair works are needed and estimate a possible date of completion.
We will then update our website on Friday, with our plan of action.
We apologise that we can't be more precise at this time, and appreciate our customers continued patience.