Update 15/05/2025 14:28
The planned dates for works near Little Moor Lane Bridge 36 in Loughborough have been amended and work will now commence on 27th May and run until 25th August.
Original 02/05/2025 11:44
Morro Partnership are undertaking the demolition of an old factory, which forms part of the canal wall and also the demolition and re-building of a 29m section of unstable wall near Little Moor Lane Bridge 36 in Loughborough https://w3w.co/epic.edge.sculpture Work will commence on the 12th May for 13 weeks until 11th August between the hours of 7am and 7pm. During the project the erection and removal of scaffolding may cause short delays lasting no more than 20 minutes. The navigation width will be reduced due to the cantilever scaffolding overhanging the canal. Please note there will be heightened activity in the area. To ensure safe passage contractors will pause work temporarily.