12/11/2018 12:06
The replacement of the lock gate originally planned at Lock 2 is being deferred to release funds to deliver other arising works in the Region.
However, a stoppage is still required to enable us to carry out urgent repairs at Locks 3 and 4. These works include unblocking the culvert on the top paddle at Lock 3 and repairs to the top gate at Lock 4 to reduce water loss.
A shorter stoppage than initially planned is needed to complete these works and so the navigation closure has been reduced by two weeks. Please note the revised dates.