28/03/2017 15:16
Towpath works have completed between Allman's Bridge and Roving Bridge and the towpath is now reopen.
Please be aware that contractors will remain on site whilst grass seed is sown in this area.
22/02/2017 15:00
Due to ground conditions, piling works are taking longer than planned, therefore towpath repairs have been delayed. The towpath will remain closed until 31st March 2017.
The navigation remains open.