Description
Third party works will be carried out to overhead power lines on the River Trent, on behalf of National Grid by specialist sub-contractor Omexon.
The planned start date is the 12th August 2024, and they will be then on site intermittently until the 3rd January 2025.
The work is taking place near Farndon, not far from Fosse Road. The nearest W3W is ///escalated.jets.window
They will be completing refurbishment of the overhead power lines (over River Trent). The work will be carried out from private land and will not affect navigational traffic or pedestrians.
Please be mindful of the works being carried out to the overhead power lines, which will involve the use of robotic technology being controlled by operatives on adjacent private land.
Please proceed with care and follow any advice from the Trust representatives on site.