30/06/2023 17:01
Repairs to the lock gate have been successfully delivered by our team.
Navigation open
29/06/2023 18:47
Planned repairs to the damaged lock gate have progressed very positively today.
We will be able to give an update on likely timescales for reopening navigation in tomorrows update
29/06/2023 08:45
Planned repairs to the damaged lock gate are progressing on site.
Updates of this notice will be provided
23/06/2023 09:40
Navigation remains closed until further notice.
Following the engineers condition assessment of the gate assisted passage is not a viable option.
We are working to deliver the repair of this damaged lock in the shortest possible timeframe.