Between Bridge 127 and 128, near Wormleighton

Detail

From Date: 29/02/2024 08:00

To Date: 29/02/2024 16:00 inclusive

Type: Navigation Closure

Reason: 3rd Party Works

Is the towpath closed? Yes

Location

Closest waterway: Oxford Canal

Starts at: Bridge 127, Stoneton Bridge

Ends at: Bridge 128, Willisons Bridge

Upstream winding hole: Near Lock 16, Marston Doles Top Lock

Downstream winding hole: Near Bridge 136, Old Fenny Compton Road

Updates

29/02/2024 17:29

Due to a change in construction methods with building a new High Speed 2 railway viaduct over the Oxford Canal, the previously planned closure of the canal is no longer required in February and March 2024.   The canal towpath will remain closed until late 2024, a waymarked alternative route has been provided by contractors working for HS2.

Description

A stoppage is required to allow HS2 to construct a new railway viaduct over the canal.