Advice: Bridge 49, Martland Mill Bridge, Leeds & Liverpool Canal

Detail

From Date: 27/02/2023 08:00

To Date: 10/03/2023 17:00 inclusive

Type: Advice

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterway: Leeds & Liverpool Canal

Starts at: Bridge 49, Martland Mill bridge

Ends at: Bridge 49, Martland Mill bridge

Description

Please be advised third-party contractors will be onsite to paint a third-party owned pipe bridge attached to Bridge 49, Martland Mill Bridge, on the Leeds & Liverpool Canal

To be able to carry out these works, a pontoon will be placed in the water.

We politely request all customers to approach the area with caution and be prepared to stop to allow the pontoon and equipment to be moved out the way for safe passage. We anticipate a wait of no longer than 30 minutes. Please listen to any advice that may be given by the onsite banksmen and to take note of the signage onsite.