Impound Station Footbridge closed

Starts: 14 July 2022 01:00 pm

Ends: 26 January 2024 09:45 am inclusive

Type: Towpath Closure

Reason: Maintenance

Is the towpath closed? Yes

Location

Closest waterwaySouth Dock
Starts atPumping Station, Impounding Station
Ends atPumping Station, Impounding Station

Updates

26/01/2024 09:56

The hording has now been removed and the bridge is reopened. Thank you for your patience during these works.

25/01/2024 11:31

The works on this bridge have been completed. However, due to the current weather conditions and material that has to be removed, it is unsafe to remove the hoarding and unlock the bridge at this time. Once the wind has dropped the hoarding will be removed and the bridge will be reopened. This will be in the next few days.

02/01/2024 12:07

Following the approval for access from Third Party landowners, a crane is booked to install the new steelwork at the impounding station bridge for 10/01/24. We are hopeful that the works will be completed before the end of January 2024

11/12/2023 15:18

Works are still planned to recommence as soon as possible. This delay is due to circumstances outside of the Trust's control. We continue to work with third party land owners to gain the access required for these works. Our contactors are also exploring other possible options

27/11/2023 14:14

We can confirm works are booked to recommence week commencing 4th December 2023. A crane will be on site for one day to lift the equipment into place We are hopeful that the works to complete the installation will be completed by mid-December.

16/11/2023 14:21

Factors beyond our control have made the original method undeliverable and we are working with adjacent land owners to get permission for plant to allow us to complete the works

15/08/2023 14:53

The Trust had hoped to replace the Impounding Station Footbridge earlier this year, but like many organisations and individuals, the challenging financial situation for us, as a charity, has made this impossible. We have now, thankfully, secured the funding required for this and this will now take place from 25/10/23 to 28/11/23 with route closures and redirections put in place during this time.

08/08/2023 09:40

We can confirm all finances have been approved and materials have been ordered. We are hopeful that this work will be completed in September.

We are sorry for any inconvenience this matter has caused and we understand your frustrations. Given the financially challenging position the Trust find ourselves in this year, these repairs could not have been undertaken any quicker.

08/09/2022 12:56

Update – This bridge will be closed indefinitely due to safety reasons. Engineers are organising inspections and liaising with the council to work together to resolve this. Any new updates will be added when more information is available

Description

Please be aware the Impound Station Footbridge west of bridge 3 is closed following an engineering inspection.