Lock 5 Rochdale Canal
Detail
From Date: 25/06/2022 12:45
To Date: 04/07/2023 09:30 inclusive
Type: Advice
Reason: Repair
Is the towpath closed? No
Location
Closest waterway: Rochdale Canal
Starts at: Lock 5, Edward Kilner
Ends at: Lock 5, Edward Kilner
Updates
04/07/2023 09:39
The lock has had a new bush but still needs gears but it works.
09/02/2023 10:57
The lock is still working on one paddle, please make sure to allow extra time when filling this lock.
We are looking to repair it when we can.
29/06/2022 17:01
. We have repaired the top side paddle and will be repairing the off side paddle next week. In the meantime, we have placed some signs to Lock 5 to assist boaters to make their own way through and to operate the lock carefully, please can this advice be followed:
Please make sure to allow extra time when filling this lock. Only one paddle is working until we can repair it.
Description
Due to an offside head paddle failure it is proving difficult to equalise the lock. To prevent water wastage this lock will now operate as assisted passage only during the hours of 9am to 3pm. Outside of these hours the lock will be chained up out of use. If you require passage during 9am and 3pm please call 0303 040 4040 and one of the local team will attend.