Ferrybridge Power Station Demolition Works - lifting pipe bridge

Detail

From Date: 25/06/2022 08:00

To Date: 29/06/2022 18:00 inclusive

Type: Navigation Restriction

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterway: Aire & Calder Navigation Main Line

Starts at: Synthetic Chemicals Bridge

Ends at: Synthetic Chemicals Bridge

Updates

16/06/2022 10:57

We have been advised of a change of date for this lift due to the police escort for the crane not being available for the previous given date.

10/06/2022 14:29

We have been advised of a change of date for this lift due to the police escort for the crane not being available for the initial date. 

Description

Contractors Keltbray are lifting a pipe bridge out from across the navigation, using a crane placed on the offside of the canal, as it is now redundant.

Can skippers of all craft please slow down when approaching the area and follow any instructions given by staff on site.

Delays of up to 20 minutes may be experienced.