Updates
25/08/2022 11:13
Midland Metro will be returning on site to complete the installation of bird mesh and brick repairs to new bridge abutments. Towpath will remain open and banksmen and signage will be utilised to manage canal traffic and pedestrians. Works to be finished on 02/09/22.
- Works on the Southern towpath - 30.08.22 - 31.08.22
- Works on the Northern towpath - 01.09.22 - 02.09.22
- No restrictions to navigation
11/07/2022 09:04
Bird mesh installation and brickwork repairs on central pier have been completed and the pontoon has been removed from canal.
Contractors will need to come back to complete further brickwork repairs and to install the bird mesh to both abutments, but these works will be carried out without closing the towpath or restricting the navigation. Banksmen and signage will be utilised to manage towpath users.
01/07/2022 15:02
Bird mesh installation and brickwork repairs have been completed on 01/07/22. However, pontoon suppliers won't be able to remove the pontoon until 08/07/22 so pontoon will remain to one side of the central pier until then.
Navigation traffic will be restricted to single lane traffic through the site until 08/07/22. Banksmen and signage will be utilised to manage canal traffic. We kindly remind boaters to take extra care when passing this section.
The northern towpath will be open on 01/07/22.
22/06/2022 15:23
The bird mesh fabricators are unable to complete their installation until 01/07/2022.
The Northern towpath will remain closed, and the pontoon installed to one side of the central pier until 01/07/2022.
Towpath access past the bridge will still be available on the Southern towpath side. Navigation will be restricted to single lane traffic through the site.
13/06/2022 08:39
Due to a delay in the fabrication of the bird mesh, remaining brickwork repairs and installation of the bird mesh will be carried out from 13/06/2022 to 24/06/2022.
The northern towpath will be closed, and a pontoon installed to one side of the central pier.
Towpath access past the bridge will still be available on the southern towpath, and navigation traffic will be restricted to single lane traffic through the site.
Banksmen and signage will be utilised to manage canal traffic. We kindly remind boaters to take extra care when passing this section