Updates
01/03/2023 15:06
We would like to advise our customers that works have progressed well at Locks 9 & 11. The navigation will now be open from 4pm on Thursday 2 March 2023
14/12/2022 15:16
We are sorry to advise that due to a delay in the lock gate production for this stoppage, a 2-week extension is required.
The delay with the lock gate production is due to essential repairs being carried out at our Bradley workshop during Autumn. This meant that the workshop was closed for several months. Due to unforeseen challenges with weather, this has meant that the workshop was closed for 4 weeks longer than anticipated. Despite our best efforts, this has caused a delay in gate production.
The stoppage will now end on 10/03/2023. We hope that this change doesn't cause any inconvenience.