04/02/2022 07:42
Contractors have advised that the piles, which are coming from Europe, have been delayed because of Covid restrictions.
The work will now start on 21st February when they are delivered.
The charity making life better by water
Making life better by water
Starts: 21 February 2022 05:30 pm
Ends: 1 April 2022 06:00 am inclusive
Type: Navigation Closure
Reason: 3rd Party Works
Is the towpath closed? Yes
Closest waterway | Calder & Hebble Navigation |
Starts at | Bridge 11, Stainland Bridge |
Ends at | Lock 4, Longlees |
Contractors have advised that the piles, which are coming from Europe, have been delayed because of Covid restrictions.
The work will now start on 21st February when they are delivered.
Contractors are carrying out piling work in relation to the installation of a new bridge associated with the A629 roadwork improvements.
Navigation traffic should not be affected as this is an overnight stoppage.
The pontoons being used may cause a restriction in the width of the canal during the daytime but boat passage will not be effected.
Can skippers of all craft slow down when approaching the site and follow any instructions given.
Please see separate notice regarding towpath diversion route.
Sign up to our monthly newsletter and be the first to hear about campaigns, upcoming events and fundraising inspiration