01/08/2021 14:14
Phase 1 has been completed and our contractors have advised the lock can be reopened earlier than expected.
The lock is now open and operational.
Thank you for your patience while these necessary works were undertaken.
30/07/2021 14:38
Contractors are being mobilised to start Phase 1 of the repair at Lock 29E starting tomorrow, Saturday 31st July, and completing Sunday 1st August.
Phase 1 will involve filling the nearside void and forming a grout curtain, allowing the canal to be reopened to navigation on Monday 2nd August.
Phase 2 of the repair will begin on Tuesday 3rd August, with a duration of 5 days, and will involve stabilising any potential voids that have occurred due to the leak to help ensure we minimise the risk of experiencing this issue again in future.
Whilst Phase 2 is being undertaken, the navigation will remain open for passage.
30/07/2021 14:24
Contractors are being immobilised to start Phase 1 of the repair at Lock 29E starting tomorrow, Saturday 31st July, and completing Sunday 1st August. Phase 1 will involve filling the nearside void and forming a grout curtain, allowing the canal to be reopened to navigation on Monday 2nd August. Phase 2 of the repair will begin on Tuesday 3rd August, with a duration of 5 days, and will involve stabilising any potential voids that have occurred due to the leak to help ensure we minimise the risk of experiencing this issue again in future. Whilst Phase 2 is being undertaken, the navigation will remain open for passage.