Conisbrough Railway Bridge
Detail
From Date: 03/05/2016 07:00
To Date: 30/10/2016 19:00 inclusive
Type: Navigation Restriction
Reason: 3rd Party Works
Is the towpath closed? No
Location
Closest waterway: Sheffield & South Yorkshire Nav
Starts at: Conisbrough Railway Bridge
Ends at: Conisbrough Railway Bridge
Updates
15/09/2016 09:49
We have been advised by the Contractor that these works have been extended until 30 October.
10/08/2016 14:31
The Contractor has discovered additional repairs which require attention whilst the scaffolding is still in place on the structure. Therefore the works are now due to finish on the 30th of September
21/06/2016 11:39
We have been advised by the Contractors that the scaffolding works are taking longer than expected and the works are now due to finish on 12 August.
Description
Contractors (Dyer & Butler) are carrying out bridge repair works using a scaffold supported from the bridge. The watercourse will be restricted at this location at points due to the delivery of materials from a barge. All boat traffic should take caution when passing and abide by the contractors advice, this may result in delay of no longer than 15-20 minutes