Wychnor lock, Trent and Mersey canal

Detail

From Date: 11/01/2016 07:30

To Date: 15/01/2016 17:30 inclusive

Type: Advice

Reason: Vegetation

Is the towpath closed? No

Location

Closest waterway: Trent & Mersey Canal

Starts at: Lock 11, Wychnor Lock

Ends at: Lock 11, Wychnor Lock

Description

Localised spot dredging is planned to be carried out at Wychnor Lock during the week commencing 11/01/2016. 

Dredging is required here due to the risk of the sluices becoming obstructed and potentially, consequent flooding.

The work will be carried out by Land and Water Services who will mobilise floating plant via Barton Turns Marina. 

The dredged silt and vegetation is to be used to top up the bank protection backfill on the off-side, between Wychnor Lock and Bridge 40, ie. immediately downstream.

The plan is to, mobilise on Monday 11th, dredge Tuesday – Thursday, then demobilise on Friday 15th.

The above is subject to weather conditions.