Lock 7, Fieldhouse & Lock 6 Riddings Lock, Huddersfield, Huddersfield Broad Canal
Detail
From Date: 08/11/2021 08:00
To Date: 04/02/2022 16:00 inclusive
Type: Navigation Closure
Reason: Repair
Is the towpath closed? Yes
Location
Closest waterway: Huddersfield Broad Canal
Starts at: Lock 7, Fieldhouse
Ends at: Lock 6, Riddings Lock
Upstream winding hole: Winding Hole - Milnsbridge Marina
Downstream winding hole: Winding hole - DS of Bridge 4, Railway
Updates
16/12/2021 12:43
Unfortunately due to further works required, we have had to extend this stoppage. The stoppage will be lifted as planned on 17/12/2021 for the Christmas period and then reinstated on 10/01/2022 until 04/02/2022. We apologise for any inconvenience.
Description
A stoppage is required to carry out the following:
Lock 7 Fieldhouse, repairs to the cill.
Lock 6 Riddings Lock, repairs required as the planking hilti nails have corroded.