Bridge 23 (Railway)

Notice Details
From Date:
28th November 2016 at 07:00
To Date:
8th January 2017 at 18:00 inclusive
Navigation Closure
3rd Party Works
Is Towpath Closed?
Notice updates:
19/09/2016 @ 14:23

It is likely that, between the removal of the existing bridge and the erection of the new bridge, there will be a period during which the navigation will be open.

This is currently projected to be between 4 December and 20 December. There will be temporary restrictions during this period but navigation should be possible. Of course, with a significant engineering project of this kind
there could be delays and it is perhaps likely that these dates will change.

If it is crucial that you are the other side of these works before the navigation is due to be open in 2017, we’d strongly recommend passing through before the works start on 28 November.


Replacing the existing bridge with a new bridge.

Lee Navigation
Starts At:
Bridge 23 (Railway)
Ends At:
Bridge 23 (Railway)
Up Stream Winding Hole:
Area just upstream of the bridge.
Down Stream Winding Hole:
Area just downstream of the bridge.