Central Docks Channel New Bridge, Liverpool Canal Link
Detail
From Date: 11/03/2019 08:00
To Date: 01/11/2019 17:00 inclusive
Type: Navigation Restriction
Reason: 3rd Party Works
Is the towpath closed? No
Location
Closest waterway: Liverpool Link
Starts at: Bascule Bridge Stanley
Ends at: Prince's Dock Bridge
Updates
01/10/2019 08:37
Please be advised these works have been extended till 1 November 2019.
08/04/2019 10:26
Please be advised third party contractors will be undergoing piling works to construct the new bridge widening abutments. These works will be facilitated between 15 April and 22 April, whilst these works are being carried out, passing craft may be asked to wait, no longer than 30 minutes, to allow the third-party contractor to cease works and allow for a safe passage.
We politely request all customers to listen to any advice that may be given by the third-party contractors onsite and to approach the area with caution.
Description
Third-party contractors will be onsite to undertake construction works to Central Dock Channel Bridge, Liverpool Canal Link. We politely request all customers to listen to any advice that may be given by the banksmen onsite.