Bridge 38, Norbury Bridge, Norbury Junction, Shropshire Union Canal

Detail

From Date: 05/11/2018 08:00

To Date: 16/11/2018 16:00 inclusive

Type: Navigation Closure

Reason: Repair

Is the towpath closed? No

Location

Closest waterway: Shropshire Union Canal

Starts at: Bridge 38, Norbury Bridge

Ends at: Bridge 38, Norbury Bridge

Upstream winding hole: Rue Hill, Grub Street Bridge 41

Downstream winding hole: Norbury Junction

Updates

14/11/2018 16:26

Following the de-watering of the navigation at Bridge 38, we were able to get a clearer picture of the missing brickwork in the towpath washwall and the repairs needed.  This was not as extensive as originally envisaged and our contractors have been able to repair the wall in a shorter time than originally expected. 

The navigation has been kept out of water for a short time to allow the mortar to cure but we are now ready to re-water, remove the portable dams and re-open the navigation ahead of schedule.

Please be aware, therefore, the end date of this stoppage has been brought forward to Friday, 16th November.

Description

Repairs needed to missing brickwork in towpath side washwall