Battery Park, Selly Oak, near Cable Bridge 80B.

Detail

From Date: 23/01/2018 19:00

To Date: 23/01/2018 19:30 inclusive

Type: Navigation Restriction

Reason: 3rd Party Works

Is the towpath closed? Yes

Location

Closest waterway: Worcester & Birmingham Canal.

Starts at: Cable Bridge 80B

Ends at: Cable Bridge 80B

Description

Interserve Construction Ltd will be installing a temporary footbridge to link the offside site compound at Bristol Road to the development site which is on the towpath side. To facilitate the works a crane will be used to lift the bridge into place. To ensure the works can be carried out safely the canal and towpath will need to be closed for a short period of time (approx. 20 minutes) during the lift. The lift is planned at 7pm on the 23rd January 2018.

Signage and banksman will be utilised to manage members of the public and canal traffic.