Manchester, Bury & Bolton Canal (Middlewood Locks)

Notice Details
From Date:
30th July 2017 at 07:00
To Date:
30th October 2017 at 17:00 inclusive
Type:
Navigation Restriction
Reason:
3rd Party Works
Is Towpath Closed?
Yes
Description:

 

 

To facilitate the demolition of the two footbridges and installation of a surface water diversion (agreement with Network Rail) 

 

Reason for Extension:

 

Due to over running works with the major Bridge and Viaduct Construction known as Ordsall Chord, over the river Irwell.

 

Delays had a knock-on effect and pushed the minor works that effect the CRT Remit to the end of the programme.

 

 

 

Location:
Manchester Bolton & Bury Canal
Starts At:
Bloody Footbridge
Ends At:
Middlewood Deep Lock