Lock 61 to 64, Johnson's Hillock, Leeds & Liverpool Canal

Notice Details
From Date:
8th January 2018 at 08:00
To Date:
2nd March 2018 at 16:00 inclusive
Type:
Navigation Closure
Reason:
Repair
Notice updates:
28/02/2018 @ 14:23

Due to the freezing conditions, we have not been able to complete the grouting and concreting works at Lock 64 today, as expected.  If weather conditions improve we will be able to re-open the navigation on Friday.  

We will issue a further update if this situation changes.

 

23/02/2018 @ 17:11

There have been some unforeseen delays in completing the large amount of work required across the Johnson's Hillock Locks. 

The team has been working additional hours and weekends but, unfortunately, will not be able to fully complete the repairs at Lock 64 by 26th February.

We are therefore extending the closure by two days and the navigation will re-open from 4pm on 28th February.

We apologise for any inconvenience this may cause.

 

 

 

Description:

Lock 64:-

Replace lock gates and repair cill.

Lock 61:-

Replace lock tail gates, extension to the lock ladder and quadrant repairs.

Location:
Leeds & Liverpool Canal
Starts At:
Lock 64, Bottom Lock
Ends At:
Lock 61, Lock 4
Up Stream Winding Hole:
Riley Green Marina
Down Stream Winding Hole:
A674 Roadbridge