23/02/2017 12:05
Note: Work at Elland Bridge will be completed by 10/03/2017
23/02/2017 10:27
Work at Crowther Bridge has been delayed due to unexpected ground conditions and difficulties in installing foundation piles. As a result of this the programme of works has been revised as additional time will be required to complete foundations and construction of washwall and towpath. The stoppage has been extended by one week, now due to finish on 17/3/17.