Bridges 13 and 22
Detail
From Date: 26/11/2016 00:00
To Date: 21/12/2016 23:59 inclusive
Type: Navigation Closure
Reason: Repair
Is the towpath closed? Yes
Location
Closest waterway: Llangollen Canal
Starts at: Bridge 13, Grange Bridge
Ends at: Bridge 22, Thomasons Bridge
Upstream winding hole: Thomasons Winding Hole
Downstream winding hole: Stonely Green Winding Hole
Updates
17/11/2016 13:35
We sincerely apologise for the lateness of this update notice, however, unfortunately we are unable to mobilise our contractors to all 4 of the Llangollen bridge wet abutment repairs before Christmas. To avoid falling behind with our planned repairs on the Llangollen bridges, which are subject to a rolling programme of underwater brickwork repairs, we now intend to undertake 2 of the repairs in January 2017. To mitigate the disruption caused by this change as far as possible, we have agreed to delay the start of the Beeston Lock closure until the completion of the Llangollen Bridge repairs to keep more of the network open. We have also instructed our contractor to work 7 days per week on the works in January.
01/11/2016 11:03
The stoppage date has been moved back due to delay procuring bespoke equipment.
Description
Full dewater and water transfer across bridge holes for brickwork repairs