Near South Accommodation Bridge

Detail

From Date: 22/02/2016 08:00

To Date: 13/05/2016 18:00 inclusive

Type: Navigation Restriction

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterway: Aire & Calder Navigation Main Line

Starts at: South Accommodation Bridge

Ends at: South Accommodation Bridge

Updates

08/04/2016 09:38

We have been advised that there have been some technical issues on site and therefore the restriction will be in place until further discussions with the Contractor and EA have taken place.

18/03/2016 12:59

Apologies, date should read completed by 24 March.

18/03/2016 09:28

We have been advised by the contractor that the works have been delayed and will now be completed by 24 April.

Currently the units have not been sunk and are sitting within the navigation. 

Please slow down and take extra care when passing this point.

Description

Contractors (WSP) are carrying out the installation of a water source heat pump. The Contractor will be installing the pump in the water next to the bank so any vessels should be aware of the operations which include a crane lift.

All users of the Public Right of Way should be aware that staff may be working on or in close proximity to the walkway/cycleway.


Caution should be taken and any cyclists should slow down whilst passing through the signed area.