Bridge 198, Churchill Bridge, Kennet & Avon Canal

Detail

From Date: 19/02/2024 08:00

To Date: 15/02/2024 08:00 inclusive

Type: Towpath Closure

Reason: 3rd Party Works

Is the towpath closed? Yes

Location

Closest waterway: Kennet & Avon Canal

Starts at: Bridge 198, Churchill Bridge

Ends at: Bridge 198, Churchill Bridge

Description

Contractors Suttle Projects will be working on behalf of Bath and North East Somerset Council to complete the new landscaping works started last year near Bath Quays Bridge south of Green Park Road. The works were delayed due to river flooding. The towpath will be closed for five days with a signed diversion in place for the duration of the works.

Please note that the boater moorings will be available but boaters may not be able to access or egress from their boats on to the towpath during the works and any stays could be affected by noise. Please observe all signs shown on site. The general public and boaters should approach the area with caution. River navigation will be unaffected.