Section of towpath between Footbridge 11A and Tinkers Leen - Nottingham Beeston Canal

Starts: 13 February 2023 12:00 am

Ends: 9 June 2023 11:59 pm inclusive

Type: Towpath Closure

Reason: 3rd Party Works

Is the towpath closed? Yes

Location

Closest waterwayNottingham & Beeston Canal
Starts atFootbridge 11A, Castle Marina
Ends atBridge 11, Tinkers Leen Crossing

Updates

31/05/2023 10:02

The third-party works currently taking place between footbridge 11A and Tinkers Leen on the Nottingham and Beeston Canal, to carry out towpath repairs, have been further extended until 9th June 2023.

The current works involve the completion of the towpath paving and re-casting of coping stone with mooring bollard.

The towpath is closed during these repairs and a diversion is in place for the duration. Moorings are also suspended and boaters are asked to be mindful of these works when travelling along the canal.

An update will be provided on the 5th June.

30/05/2023 11:27

The third-party works currently taking place between footbridge 11A and Tinkers Leen on the Nottingham and Beeston Canal, to carry out towpath repairs, have been further extended until 9th June 2023.

The current works involve the completion of the towpath paving and re-casting of coping stone with mooring bollard.

The towpath is closed during these repairs and a diversion is in place for the duration. Moorings are also suspended and boaters are asked to be mindful of these works when travelling along the canal.

An update will be provided on the 5th June.

26/05/2023 12:40

The third-party works currently taking place between footbridge 11A and Tinkers Leen on the Nottingham and Beeston Canal, to carry out towpath repairs, have been further extended until 5th June 2023.

The current works involve the completion of the towpath paving and re-casting of coping stone with mooring bollard.

The towpath is closed during these repairs and a diversion is in place for the duration. Moorings are also suspended and boaters are asked to be mindful of these works when travelling along the canal.

27/04/2023 15:45

The third party works currently taking place between footbridge 11A and Tinkers Leen on the Nottingham and Beeston Canal, to carry out towpath repairs, have been further extended until 31st May 2023 due to resourcing issues with their contractors.

The towpath is closed during these repairs and a diversion is in place for the duration. Moorings are also suspended and boaters are asked to be mindful of these works when travelling along the canal.

20/03/2023 10:55

Third party works are currently taking place between footbridge 11a and Tinkers Leen on the Nottingham Beeston Canal, to carry out towpath repairs.

This has been extended until the 30th April, to allow new concrete to cure sufficiently that the mooring bollards can be used without being loosened.

The towpath is closed during these repairs and a diversion is in place for the duration. Moorings are also suspended and boaters are asked to be mindful of these works when travelling along the canal.

Description

A third party works programme of repairs to the towpath between footbridge 11A and Tinkers Leen on the Nottingham & Beeston Canal will take place between 13th February and 31st March.

The work will involve piling sections of the canal wall and reinstating the sections of towpath where subsidence has occurred.

The towpath will be closed during these repairs and a diversion will be in place for the duration.

The piling will be carried out from the waterway and therefore moorings will be suspended during this time. This may also restrict the navigation and so boaters are asked to be mindful of these works when travelling on the canal.

Thank you for your patience while these works are carried out.