Updates
13/01/2023 19:04
Our contractor needs an additional week to prepare equipment and materials for this stoppage, so it will begin a week later, starting on 30/01/2023.
They will make this week up and finish at the same end date as previously advised (17/3/23).
We are sorry for any inconvenience caused.
23/12/2022 08:45
We would like to advise that following a further review of this project, our contractors have advised that less time than initially planned is required to carry out these works. Therefore, the start date will be pushed back from 03/01/2023 to 23/01/2023. We apologise for any inconvenience caused.