Canning River Entrance Gate, Liverpool South Docks

Detail

From Date: 07/04/2022 13:00

To Date: 01/11/2022 08:00 inclusive

Type: Navigation Closure

Reason: Structure failure

Is the towpath closed? No

Location

Closest waterway: Liverpool Link

Starts at: Canning River Swing Bridge

Ends at: Canning River Swing Bridge

Updates

04/11/2022 15:53

We are pleased to advise Canning River Entrance Gate, Liverpool has been repaired and navigation via this lock has resumed.

04/10/2022 14:20

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to navigation whilst we continue repairs.

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided by Monday 7 November.

14/09/2022 10:58

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to navigation whilst we continue repairs.

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided by Friday 7 October.

26/08/2022 10:46

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to navigation. Further issues have been identified and contractors have been informed.  

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided by Friday 16 September.

05/08/2022 16:33

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to navigation.

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided by Friday 26 August.

29/07/2022 16:12

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to navigation.

Our team have been to site today and completed a repair, with further works required.

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided by Friday 5 August.

21/07/2022 11:38

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to navigation due to a mechanical failure.

Our specialist contractor has been delayed to site and is due to attend within the next week to inspect the issue and provide a timescale of repair.

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided by Friday 29 July.

15/07/2022 15:02

Please be advised, due to a mechanical failure, Canning River Entrance Gate, Liverpool South Docks is closed to navigation.

Our specialist contractor is due to attend Wednesday 20 July to inspect the issue and provide a timescale of repair.

Please note this does not affect Salthouse Dock bookings coming in via the Liverpool Canal Link.

A further update will be provided Thursday 21 July.

08/07/2022 11:45

The further works required to the system at Canning River Entrance Gate, Liverpool South Docks have been arranged for Wednesday 13 July, including further testing on the gate itself.

Whilst access through Canning River Entrance Gate remains available, our specialist M&E team will need to continue overseeing all passages. To book a passage, please call our North West team on 0303 040 4040, Monday to Friday.

Whilst works continue, bookings will be available Monday to Friday, tide dependant. Weekend bookings will not be permitted at this time.

A further updated will be provided by Friday 15 July.

24/06/2022 16:05

We are pleased to advise that Canning River Entrance Gate, Liverpool South Docks has now been repaired and is operational to boats wishing to enter Liverpool South Docks via the River Mersey, and vice versa.  

However, whilst passage is possible, further works are needed to reinstate the back-up system. Due to this, our specialist M&E team will need to oversee all passages.

To book a passage, please call our North West team on 0303 040 4040, Monday – Friday. Whilst works continue, bookings will be available Monday to Friday, tide dependant. Weekend bookings will not be permitted at this time.

A further update will be provided Friday 8 July.

10/06/2022 10:13

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to operation. A major fault has occurred which is making the gate inoperable, and now needs a replacement part.

Our teams are sourcing the necessary replacement, however as the valve is unique, it will be sourced from oversees and we do not have a confirmed date of delivery.

Please note, this does not affect customers coming in and out of Liverpool South Docks via the Liverpool Canal Link.

An update will be provided by Friday 24 June. 

27/05/2022 14:51

Please be advised Canning River Entrance Gate, Liverpool South Docks remains closed to operation. Localised training on the operation of the new system is scheduled for 30th and 31st May and a valve replacement has been ordered, with delivery and installation estimated to be week commencing 6th June.

Please note, this does not affect customers coming in and out of Liverpool South Docks via the Liverpool Canal Link.

An update will be provided by Friday 10th June.

13/05/2022 16:37

Canning River Entrance Gate, Liverpool South Docks remains closed to operation whilst our contractors continue works the control system with final tests scheduled for next week. Localised training on the operation of the new system will then take place week commencing Monday 23 May.

Please note, this does not affect customers coming in and out of Liverpool South Docks via the Liverpool Canal Link.

An update will be provided by Friday 27 May.

14/04/2022 11:48

Canning River Entrance Gate, Liverpool South Docks remains closed to operation. Our teams are working on the control system, and we anticipate these works could take 1 month. We will endeavour to advance on this time.

Please note, this does not affect customers coming in and out of Liverpool South Docks via the Liverpool Canal Link.

An update will be provided by Friday 13 May.

Description

Please be advised, due to a mechanical failure with the hydraulic system, navigation through Canning River Entrance Gate, Liverpool South Docks is closed.

Our specialist hydraulic contractor is on site establishing a method of repair, following which we will then source the required replacement parts.

An update will be provided by Thursday 14 April.