25/03/2022 16:31
Further to the notice below, we are delighted to report that our contractors have cleared the trees that were blocking the navigation by Bridge 119 ahead of their estimated plan.
There is still debris in the canal which will be cleared on Monday and the navigation will be reopened following this clearance and engineers inspection.
You are welcome to contact us on enquiries.walessouthwest@canalrivertrust.org.uk if you would like to discuss this information with a member of our Customer Service Team.
23/03/2022 17:12
Our contractors have confirmed they will mobilise to site on Thursday 24th March to remove the remains of this tree which are blocking navigation.
Due to the size and instability of the root plate and the slope of the ground they anticipate this work could take five days to complete.
We will update with further progress when we are able to.