Enterprise Wharf, Birmingham, Digbeth Branch (Birmingham & Fazeley Canal)
Detail
From Date: 14/02/2022 08:00
To Date: 11/03/2022 17:30 inclusive
Type: Navigation Restriction
Reason: 3rd Party Works
Is the towpath closed? No
Location
Closest waterway: Digbeth Branch (Birm'm & Fazeley)
Starts at: Parkes Basin Bridge
Ends at: Parkes Basin Bridge
Updates
04/03/2022 09:33
Due to issues with removal of site equipment, the finish date will now be Friday 11th March.
11/02/2022 15:32
Please be advised that the finish date has been changed. The works will now take place until Friday 4th March.
Description
The navigation and towpath will remain open. Graham Group have been redeveloping the site at Enterpirse Wharf and as part of that development, they need to reconnect the surface water discharge pipe into the canal. To do this safely, a fabric dam will be installed within the navigation for the duration of the works. Signage will be posted up and down stream of the works area. We kindly ask our customers to take extra care when passing through this area.