Keadby Rail Drawbridge, Bridge 83

Detail

From Date: 14/09/2021 06:00

To Date: 18/11/2021 09:45 inclusive

Type: Advice

Reason: Information

Is the towpath closed? No

Location

Closest waterway: Stainforth & Keadby Canal

Starts at: Bridge 83, Keadby Rail Drawbridge

Ends at: Keadby Lock

Updates

18/11/2021 09:42

We have been advised by Network Rail that repairs have been carried out to the bridge and that the restrictions have been lifted. 

08/11/2021 13:14

Please see below further dates proposed by Network Rail for passage between 12:00 - 13:00

Tuesday 9th November

Thursday 11th November

Tuesday 16th November

Thursday 18th November

Tuesday 23rd November

Thursday 25th November

Tuesday 30th November

Thursday 2nd December 

Any craft wishing to pass through the bridge must be present by 12:00 on the above dates.

05/11/2021 10:24

Network Rail are still carrying out the repairs and will be able to give a further update after the 14th November.

Unfortunately, the opening date of the 28th October was unable to happen due to further repairs still being required.

We will update the notice when we receive further information from Network Rail.

25/10/2021 13:45

Due to Network Rail's plant and electrification team having to undertake duties on an equipment failure elsewhere they will not be able to resource the planned opening of Keadby rail drawbridge on the 26th October as below.

Normal service will resume on the opening dates from Thursday 28th October and continue as normal.

04/10/2021 09:15

Please see below advised dates proposed by Network Rail for passage through Keadby Rail Drawbridge, 83.

Tuesday 12th of October 

Thursday 14th of October 

Tuesday 19th of October 

Thursday 21st of October 

Tuesday 26th of October 

Thursday 28th of October

Tuesday 2nd of November 

Thursday 4th of November 

Any craft wishing to pass through the Bridge must be present by 12:00 on the above date/s.

You may experience a delay of up to 1 hour to allow Network Rail to operate the Bridge around rail traffic.

Network Rail will only be operating the Bridge for one opening within each specified window in order to mitigate any failure.

This notice will be updated with any future dates once these have been confirmed by Network Rail.

30/09/2021 16:01

Network Rail have advised that Keadby Rail Drawbridge will be available for limited passage on the following dates and times- 

Tuesday 05/10/2021

Thursday 07/10/2021

Any craft wishing to pass through the Bridge must be present by 12:00 on the above date/s.

You may experience a delay of up to 1 hour to allow Network Rail to operate the Bridge around rail traffic.

Network Rail will only be operating the Bridge for one opening within each specified window in order to mitigate any failure.

This notice will be updated with any future dates once these have been confirmed by Network Rail. 

22/09/2021 10:01

Network Rail have advised that Keadby Rail Drawbridge will be available for limited passage on the following dates and times- 

Thursday 23/09/2021

Tuesday 28/09/2021

Thursday 30/09/2021

Any craft wishing to pass through the Bridge must be present by 12:00 on the above date/s.

You may experience a delay of up to 1 hour to allow Network Rail to operate the Bridge around rail traffic.

Network Rail will only be operating the Bridge for one opening within each specified window in order to mitigate any failure.

This notice will be updated with any future dates once these have been confirmed by Network Rail.

Description

Network Rail will be carrying out an inspection and starting repair works at Keadby Swing Bridge on Tuesday the 14th of September.

Due to these repair works navigation will be closed from Vazons Swing Bridge to Keadby Lock until the repair works are complete.

Once we have received an update from Network Rail this notice will be updated accordingly.