Installation of mooring walkway on the off-side of the canal approximately 200m long between Bridge 3 Violet Road and Bridge 4 Bow Common Lane

Detail

From Date: 19/07/2021 08:00

To Date: 13/09/2021 18:00 inclusive

Type: Advice

Reason: 3rd Party Works

Is the towpath closed? No

Location

Closest waterway: Limehouse Cut

Starts at: Bridge 3, Violet Road

Ends at: Bridge 4, Bow Common Lane

Updates

21/06/2021 17:10

Please be advised that works have been delayed until the 19th of July

Description

The width of the waterway will be reduced to a minimum of 9m to allow a pontoon based excavator and piling equipment to be used to install a new mooring walkway on the offside of the canal.

Please proceed with care on this section of waterway.

Pontoons to be craned in a Bow Free Wharf on 21/06/2021.