Watford Lock Flight, Leicester Line (Grand Union Canal)

Detail

From Date: 17/01/2022 08:00

To Date: 25/02/2022 16:00 inclusive

Type: Navigation Closure

Reason: Repair

Is the towpath closed? Yes

Location

Closest waterway: Leicester Line (Grand Union Canal)

Starts at: Lock 1

Ends at: Lock 7

Upstream winding hole: Adjacent to Bridge 7, Ashby's Bridge

Downstream winding hole: Below Watford Lock 1, bottom lock.

Updates

28/10/2021 12:40

We have had to alter the date of this stoppage due to issues with sourcing timber materials. This has caused delays to the production of lock gates and has meant that the gates for this stoppage will not be ready for the original planned stoppages dates.

The new stoppages dates that we are publishing now will mean that this work will still be carried out during the Winter months and ensures the gates will be fit for use during the Summer.

Description

A stoppage is required to  carry out repairs at Watford Locks as follows: 


Lock 1 – Improvements to the lock ladder and repairs to address leakage
Lock 3 – Replacement of the bottom lock gates
Lock 4 – Repointing of brickwork below the copings
Lock 5 – Brickwork repairs within the lock chamber
Lock 6 – Brickwork repairs within the lock chamber
Lock 7 – Replacement of the top and bottom gates