18/02/2022 13:51
This Stoppage has been extended. We have taken the decision to extend this Stoppage. This is to undertake the additional work of replacing the gates at Lock 7, this Stoppage will now be completed on 04/03/2022. The gate replacement at Lock 7 was due to take place in a future Stoppage but the new gates are ready ahead of schedule and it is thought carrying out the works now will be of most benefit to canal users. We apologies for any inconvenience caused.
28/10/2021 12:40
We have had to alter the date of this stoppage due to issues with sourcing timber materials. This has caused delays to the production of lock gates and has meant that the gates for this stoppage will not be ready for the original planned stoppages dates.